NON-STRUCTURAL SEISMIC UPGRADE OF THE IMPERIAL COUNTY

PROJECT LOCATION: EL CENTRO, CA
COST: $571,288
CLIENT: CITY OF EL CENTRO
ARCHITECT: HOLT ARCHITECTS
YEAR COMPLETE: 2013

The non-structural seismic upgrade project incorporates night work, with construction phased within the building to accommodate all departments within this active County facility. The initial phase ids comprised of demolition of the existing ceiling and ceiling grid in an existing two story building.  New ceiling, insulation and seismic-protected ceiling grid and tiles to be installed with architectural finishes to the ceiling layout.  The existing HVAC and electrical systems to be reconfigured for the new layout. Owner generated scope also includes the installation of vertical and horizontal expansion joint system on the exterior of the building.  Project completed within 60 days.